This article explores how a neutral mediator developed an informal approach tailored to the circumstances in a dispute that compromised the development of a power plant. The goal, as in all project ADR, was to provide the developer and contractor with a non-binding mechanism for reaching a solution that would:
(1) not adversely affect the ongoing project work;
(2) not alienate the parties from each other; and
(3) keep both parties away from the courts, with their lengthy and costly litigation process and uncertain outcomes.
Recommended Citation
Grynbaum, Joe
(1999)
"Mediating a powerful dispute effectively,"
ADR Bulletin:
Vol. 2:
No.
5, Article 1.
Available at:
http://epublications.bond.edu.au/adr/vol2/iss5/1